Pune's 10 Most-Delayed MahaRERA Possessions in 2026 (Live)
Years past their original possession date. Less than 90% built. Still selling. Auto-updated every hour from MahaRERA's public records.
When a builder registers a project on MahaRERA, they sign a number into the public record: the date they promise to hand over possession. That date is the contract you're effectively signing when you book.
Then the date moves. Then it moves again. Most buyers find out years later.
This page is a live ranking of Pune projects whose original possession date is furthest in the rear-view mirror - and which are still substantially unbuilt. Every hour, we re-scan every project on MahaRERA, compare today against the original date the builder signed up for, and re-sort. The list updates as MahaRERA's records change.
Follow projects in one dashboard
Create a RERAdetails account to save the projects and builders you care about. Automatic change alerts and newsletters are coming soon.
| # | Project | Status | Delay | Slowest building | Originally | Now promising | |
|---|---|---|---|---|---|---|---|
| 1 | SONCHAFA Vastushilp P52100008160 | Active · Selling | 8.8 yr late | 43% | Dec 2017 | Apr 2028 | View → |
| 2 | Tamara Goldfinger Kataria Urban Developments P52100013230 | Active · Selling | 8.8 yr late | 42% 3 of 5 done | Dec 2017 | Aug 2027 | View → |
| 3 | RAMNAGAR HOUSING COMPLEX PHASE L VAASTU UDYOG P52100008598 | Active · Selling | 8.5 yr late | 89% | Mar 2018 | Apr 2027 | View → |
| 4 | Rakshak Vatika A B C wings URBAN LIFE REALTY LLP P52100000381 | Active · Selling | 8 years late | 0% | Oct 2018 | Oct 2027 | View → |
| 5 | Defence Colony Pune Phase4 Defence Colony Pune P52100009756 | Active · Selling | 7.8 yr late | 82% | Dec 2018 | Nov 2026 | View → |
| 6 | K K SUNDARBAN BUILDING H K K DEVELOPERS P52100004320 | Active · Selling | 7.8 yr late | 70% | Dec 2018 | Apr 2027 | View → |
| 7 | POLARIS KESHAVLEELA PROPERTIES P52100009759 | Active · Selling | 7.8 yr late | 13% 1 of 4 done | Dec 2018 | Jun 2027 | View → |
| 8 | R K PRIDE PANKAJ KASHINATH PATIL P52100009450 | Active · Selling | 7.8 yr late | 81% | Dec 2018 | Nov 2027 | View → |
| 9 | Suvarna Alay Maheshwari Developers P52100006825 | Active · Selling | 7.8 yr late | 82% | Dec 2018 | Apr 2027 | View → |
| 10 | Suyash Greens Suyash Promotors & Developers P52100003942 | Active · Selling | 7.8 yr late | 85% | Dec 2018 | Oct 2026 | View → |
What the data tells you
Read across two columns: Originally is what the builder promised when they registered. Now promising is the latest revised date they've put on file with MahaRERA - in red when it's not the original.
The pattern is the story. Nearly every project at the top of this list has revised its possession date - most of them multiple times, by years. A 2017 promise becomes a 2027 promise becomes a 2030 promise. Each revision is a one-line filing; no court order, no buyer signature required.
A project still showing Active · Selling in the Status column is one that MahaRERA still allows to advertise and book new flats - regardless of how many years past its original deadline it is. The two facts coexist on the portal. They should be considered together.
What we filtered out
This list shows only projects in an active building lifecycle - currently registered, not lapsed, not under abeyance, not de-registered. Completed projects aren't here, even if they delivered late. Projects MahaRERA has formally suspended aren't here either.
We also drop projects where every building is 90%+ built. Many builders get the municipal occupancy certificate, hand over flats, and just never bother to file the formal Form 4 closure on MahaRERA. On paper that project still looks 8 years late. In reality the buyers moved in years ago. We don't include those here.
That filter matters: it means everything you see on this page is a project where buyers are still waiting for keys in at least one building, AND construction itself is still meaningfully incomplete.
How to read the columns
Delay compares today against the original promised completion date. Slowest building is the construction completion of the least-built building in the project - because phased projects often hide one stuck tower behind several delivered ones, and the slowest one is what a prospective buyer of that tower cares about. When a project has multiple buildings, we also surface how many are already done. Red on the slowest building (<30%) means barely off the ground after years; amber (30-59%) means significant work still pending. Originally is what the builder first promised; Now promising is the latest revised date, shown in red when it's not the original.
Track every revision on a project you care about
Open any project page to save it to your RERAdetails dashboard. Automatic change alerts are coming soon.
Browse Pune projects →What we track
Every Pune project registered on MahaRERA is on our daily radar. We pull 25 separate data feeds per project - possession-date revisions, complaints, litigation, sale-deed registrations, construction progress, financials, and document uploads - and flag every change for analysis. Subscriber alerts are coming soon.
We don't edit, weight, or filter the official numbers. What you see is what MahaRERA's own systems report, just made sortable, comparable, and impossible to bury.
See the most-complained Pune projects → · Browse all Pune projects →